A leading global engineering firm required a reliable and efficient solution for handling solvent collection at a major semiconductor manufacturing site in Phoenix, Arizona. The project demanded a turnkey system capable of integrating seamlessly with existing infrastructure while meeting stringent operational and safety requirements.

Industry

Semiconductor Manufacturing

Challenge

Integration and Safety

Solution

Turnkey Solvent System

Challenge

The client faced several challenges in this project:

  • Operational reliability: The solvent collection process needed a system that could operate continuously with minimal downtime
  • Ease of integration: The system had to be pre-engineered and prepackaged to reduce on-site construction, permitting, and engineering complexity
  • Safety and compliance: The system required precise controls and documentation to meet strict environmental and workplace safety regulations
  • Training and support: Operators needed hands-on training to ensure smooth adoption and long-term system performance

 

Solution

Burt Process engineered and delivered a turnkey solvent collection and treatment station designed specifically for high-reliability applications in semiconductor manufacturing.

solvent-collection-and-treatment
solvent-collection-and-treatment-2

Key solution elements included:

  • Prepackaged system: Fully assembled, integrated, and factory-tested equipment prior to shipment to ensure performance
  • Engineering documentation: Complete submittal package with system layout drawings, P&IDs, bills of materials, and PLC ladder logic diagrams
  • Installation support: Coordination with client’s contractors for offloading, rigging, plumbing, and compressed air connections
  • On-site services: Three days of start-up, training, and commissioning, ensuring operators were confident in system operation
  • Comprehensive manuals: Detailed operating, troubleshooting, and maintenance guides provided electronically

 

Results

  • The engineered system provided the client with:
  • A ready-to-install solution that minimized installation complexity and risk
  • Improved operational efficiency with robust, reliable equipment
  • Assurance of regulatory compliance with safety instrumentation and documentation
  • Empowered staff through structured training and commissioning support